Billing History Part 2

This guide walks you through the full process — from initial setup to archiving your completed forms.

For an in depth video walkthrough please visit peAk and watch our Lunch & Learn here:

Overview

The Billing History Workbook (billingHistory_v04.03.xlsm) is an Excel-based tool that connects directly to your INNERGY project data via API to generate two standard billing documents:

● Form A — Billing Worksheet (SOV continuation sheet / AIA G703-style)

● Form B — Application and Certificate for Payment (cover sheet / AIA G702-style)

Prerequisites

● Microsoft Excel (macros must be enabled)

● Your INNERGY API Key

● The billingHistory_v04.03.xlsm workbook

● An active INNERGY project with a Schedule of Values

Once all prerequisites are confirmed, follow these 11 steps to complete your billing draw from INNERGY to your final AIA payment application.

Step 1 — Enable Macros

When you first open billingHistory_v04.03.xlsm, Excel will prompt you to enable macros.

1. Click Enable Content in the yellow security bar at the top of Excel.

2. Macros must be enabled for the workbook's import/export buttons to function.

⚠️ If you do not see the Enable Content prompt, go to File → Info → Enable Content.

Step 2 — Enter Your API Key

The workbook connects to INNERGY using your personal API key.

3. Navigate to the Project Summary tab.

4. Locate the API Key: field in the upper-left area of the sheet.

5. Enter your INNERGY API key in the cell to the right of the label.

💡 Finding your API key: In INNERGY, go to your user profile/settings and look for the API Key section. Copy and paste it directly into this cell.

Step 3 — Import Project Data from INNERGY

Once your API key is entered, pull in your project's data.

6. On the Project Summary tab, locate the Import button (or the designated data-refresh control).

7. Click it to connect to app.innergy.com and pull your project's information.

8. The following fields will populate automatically from INNERGY:

Field

Source

Project Number

INNERGY Project #

Project Name

INNERGY Project Name

Customer

INNERGY Customer Name

Project Manager

Assigned PM in INNERGY

PM Email

PM's email address

Project Status

Current status in INNERGY

Project Address

Project location fields

9. Verify the populated data matches the correct project before proceeding.

Step 4 — Configure Tax & Retainage Option

10. On the Project Summary tab, locate the Tax & Retainage Option field.

11. Select the appropriate setting from the dropdown (e.g., Tax Before Retainage Held).

12. This setting controls how taxes are calculated across Forms A and B.

Step 5 — Review the Draw Data

The draw Data tab is the source of your SOV line items, pulled from INNERGY.

13. Click the draw Data tab.

14. Confirm the following columns are populated correctly:

Column

Description

Item #

SOV line item number

Description of Item

Line item description

Scheduled Value

Original scheduled value (pre-tax)

Sales Tax

Tax applied to the line item

Total Scheduled Value

Scheduled Value + Sales Tax

From Previous Application

Amount billed in prior draw(s)

This Period

Amount to bill in the current draw

15. If line items are missing or incorrect, verify the SOV is set up properly in INNERGY before re-importing.

Step 6 — Enter Current Period Billing Amounts

★ KEY DATA-ENTRY STEP — This is the only step where you enter dollar amounts for the current draw. All prior billed amounts carry forward automatically.

16. On the draw Data tab (or directly on Form A), locate the This Period column.

17. Enter the dollar amount you are billing for each SOV line item in the current draw.

18. The workbook will automatically calculate:

○ Total Completed & Stored (Previous + This Period + Stored Materials)

○ % Complete per line item

○ Balance to Finish

○ Retainage (if applicable)

💡 Enter only the current period amounts. Prior billed amounts are carried forward automatically.

Step 7 — Enter Application Details

19. Return to the Project Summary tab.

20. Fill in the following fields:

Field

Description

Invoice Number

Your invoice number for this draw

Application Number

Sequential draw number (e.g., 1, 2, 3…)

Application Date

Date of this billing application

Period From

Start date of the billing period

Period To

End date of the billing period

Step 8 — Review Form A (Billing Worksheet)

21. Click the Form A tab.

22. Confirm all SOV sections are correct:

Form A — SOV sections

● Original Contract line items and totals

● Approved Changes section

● Current Contract total

● Pending Changes section

Form A — Header and totals

23. Verify the header information: Project Name, Client Name, Application Number, Period To, Contract #.

24. Confirm column totals match expected values before printing.

Step 9 — Review Form B (Application and Certificate for Payment)

25. Click the Form B tab.

26. This form summarizes the full billing application. Confirm the following fields at the top of the form:

Form B — Header fields

● To General Contractor / Attn fields (if applicable)

● Project name

● From Contractor (your company name from INNERGY)

Form B — Financial summary lines

Verify each line in the financial summary section:

Line #

Field

Description

1

Original Contract Sum

Total contract amount at signing

2

Net Change by Change Orders

Sum of all approved change orders

3

Contract Sum to Date

Lines 1 + 2

4

Total Completed & Stored to Date

Cumulative work completed including materials stored

5

Retainage

Held-back percentage per contract terms

6

Total Earned Less Retainage

Line 4 minus Line 5

7

Less Previous Certificates for Payment

Total already paid in prior draws

8

Current Payment Due

Line 6 minus Line 7 — amount due this draw

27. Verify the Invoice Number and Subcontract # fields are populated.

Step 10 — Print / Export Forms

28. With Form A or Form B active, use the workbook's Export button (or standard Excel print) to generate your output.

29. Recommended: Export as PDF for submission to the General Contractor or Owner.

30. Print both Form A and Form B as a complete billing package.

Step 11 — Archive the Completed Forms

After the draw is approved and submitted:

31. Use the workbook's Archive function (button on the Project Summary or dev tab) to save a snapshot of this draw period.

32. Archiving preserves the current period data so it rolls forward correctly as "From Previous Application" in the next draw.

33. Confirm the archive was successful before entering data for the next billing period.

⚠️ Do not skip archiving. Failing to archive before starting the next draw will cause incorrect carry-forward amounts in Forms A and B.

Troubleshooting

Issue

Solution

Data does not import from INNERGY

Verify your API key is entered correctly with no extra spaces

Line items are missing from draw Data

Check that the SOV is fully set up in INNERGY and re-import

Retainage calculations look wrong

Confirm the Tax & Retainage Option setting on Project Summary

Macros are disabled

Click Enable Content in the Excel security bar and reopen

Form totals don't match

Ensure "This Period" values are entered only in the draw Data tab, not overridden manually on Form A

Recent Updates and Improvements:

v 04.03:

Corrected a formula error on Form B. The formula in cell O36 should be:

=originalContract[[#Totals],[This Period]] + approvedChanges[[#Totals],[This Period]]

You can use this formula to correct any of your existing workbooks as well.